To simplify the requirements of the documentation on placement of the customer’s electrical faciliti…

To simplify the requirements of the documentation on placement of the customer’s electrical facilities, which shall be attached to its hook-up application, excluding the necessity to attach the detailed replication from the topographical and geodetic plan at a scale of 1:2000 indicating the location of the power facility, land plot or planned connection point.

Based on the report:

State:

National Energy and Utilities Regulatory Commission,

Status:

Implemented

— comments: In accordance with the clause 4.4.2 of Section 4.4 of the Code on Distribution Systems, only the general "replication from the topographical and geodetic plan or building plan indicating the location of the land" shall be attached to the hook-up applicati