The Business Ombudsman Council provides recommendations to state bodies on the basis of individual cases and in accordance with published systemic reports. Here we have collected information on the implementation status of systemic recommendations only.
Report name
|
Issued recommendations
|
Execution status
|
---|---|---|
Systemic report "Natural monopolies vs. competitive business: how to improve relations" |
To develop amendments to the Law of Ukraine “On regulating Urban Development Activities” to encourage local governments to develop territorial and detailed zoning plans. Ministry of Regional Development, Construction and Residential Services |
Implemented
— comments:
Implemented in a different way.
|
To develop amendments to the Law "On regulating urban development activities" regarding the cancellation of developer's equity contribution as an outdated mechanism that is applied in a non-transparent way and appears to be an indirect tax, which is forbidden by law. Ministry of Regional Development, Construction and Residential Services |
Implemented
|
|
To organize public hearings with business associations, experts and the community to come up with better instruments for territorial development on a transparent basis. Ministry of Regional Development, Construction and Residential Services |
Implemented
|
|
National Energy and Utilities Regulatory Commission |
Implemented
— comments:
There is a final (but not yet approved with the Energy Community) Draft Methodology (order) for the formation of the fee for hooking-up to transmission and distribution systems.Also, according to the clause 4.6.2 of the Code on Distribution Systems in the case of standard and non-standard “turnkey” hook-up, the development of design and appraisal documentation for the electrical installation of external power supply is carried out by the DSO (and includes an input device with a switching device).Meanwhile, the technical specifications contain requirements for engineering maintenance in the customer's networks and, accordingly, the design and construction thereof shall be ensured by the Customer; the terms of reference (technical task) contain the requirements for engineering maintenance in the DSO networks and, accordingly, their design and construction shall be carried out by the DSO
|
|
National Energy and Utilities Regulatory Commission |
Implemented
— comments:
There is a final (but not yet approved with the Energy Community) Draft Methodology (order) for the formation of the fee for hooking-up to transmission and distribution systems.
|
|
National Energy and Utilities Regulatory Commission |
Implemented
— comments:
In May 2017 the NEURC has developed and provided on its website an Estimated Cost Calculator for the standard hook-up service: http://www.nerc.gov.ua/?calc=ok Furthermore, the formula for calculating the fee for non-standard connection, contained in the Draft Methodology (order) for the formation of the hooking-up fee for the transmission and distribution systems, allows to calculate the cost of such a hook-up in advance
|