The Business Ombudsman Council provides recommendations to state bodies on the basis of individual cases and in accordance with published systemic reports. Here we have collected information on the implementation status of systemic recommendations only.

Report name
Issued recommendations
Execution status

Systemic report "Getting access to electricity"

To hook up a customer’s power unit to power network pursuant to contract only (without filing a separate application).

Ministry of Regional Development, Construction and Residential Services

In process
— comments: In accordance with the Section 3 of the Code on Distribution Systems, the DSO/oblenergo implements long-term planning for the development of the distribution system, including conducting all the necessary researches and assessments/forecasts. For this purpose, the DSO develops a DSO Development Plan, which is to be submitted for approval to the Regulator in accordance with this Code.The DSO Development Plan is a document that contains the planned items of new construction, reconstruction and technical re-equipment of the distribution system for the next 5 calendar years, with the definition of the required amount of investment and the timing for the implementation of the relevant measures.Therefore, we assume that the electrification of a certain territory may be included to the DSO development plan.